Research on Progress Control of Overseas Cement EPC General Contracting Project
Jianke Gu
Show Less
1 Suzhou Sinoma Construction Co., Ltd., Suzhou 215300, Jiangsu Province, China,
JWA 2021 , 5(6), 42–46; https://doi.org/10.26689/jwa.v5i6.2756
© 2021 by the Authors. Licensee Whioce Publishing, Singapore. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution 4.0 International License ( https://creativecommons.org/licenses/by/4.0/ )
Abstract

The purpose of Engineering Procurement Construction (EPC) general contracting project schedule management is to ensure that the project meets its deadlines, and it plays a critical role in contract performance. In comparison to the domestic general contracting model, project management and coordination are more complex for the general contractor of international EPC projects. As a result, scientific project schedule process control is critical to effectively ensuring project duration, saving project costs, improving project management level, and project quality, and ensuring that the project achieves the promised advantages for both the contractor and the owner. Through the research and analysis of the status of the schedule management of the Indonesia B Project Phase II cement project, corresponding optimization measures are proposed for the project schedule process control.

References
Kirzner H, 2014, Project Management-A Systematic Approach to Plan Schedule and Control. Beijing: Publishing House of Electronics Industry, (06).
Li J, 2014, EPC Cement Engineering Project Schedule Management Research and System Development. Concrete Engineering, 4(26): 3459-3460.
Liu L, 2018, Analysis of Progress Management of Overseas Cement Plant Projects. Architectural Engineering Technology and Design, 24: 3073.
Cao W, 2017, Analysis of Progress Control and Restrictive Factors of International EPC Engineering Projects. Project Management Technology, (12):46-50.